|
The anagama kiln at Wysing
Arts Centre in Cambridgeshire UK, was built by Izumihara Masanobu and other
volunteers including Paul McAllister and Stephen Parry over the summer of
1997. Paul, Steve and myself have been firing the kiln since 1998. This kiln
is much more challenging to fire than the Loughborough kiln due to the smaller
firebox ( very small relative to the chamber size), and the lack of a grate
(the fuel being dropped directly onto the kiln floor). The kiln was originally
built to fire to around 1250C. The work that was fired in it was cyclical,
in that, Masanobu only anticipated getting the front stack of pots out as
finished. He packed the back of the kiln with pots to be bisc fired. These
pots would then be at the front of the stack in the next firing. We have always
attempted to fire to 1300C plus in this kiln, which we have achieved each
time with around cone 10 (1280C) at the back.
In 2000 a
salt chamber which was built by Paul and myself between the back of
the anagama and the chimney, was knocked down and the chimney rebuilt
to the correct dimensions for the anagama chamber and firebox size. This
improved the firings considerably, the draw from the chimney now not being
compromised by the volume of the salt chamber. It still took immaculately
timed and delivered side stoking with split pine to coax the temperature
to where we wanted it to be. The results produced from this kiln vary
from the Loughborough kiln due to the variation in kiln design. The shape
of this kiln is a more exaggerated upside down boat shape which creates
its own unique micro climates and flame channels through the work within
the packing space. Also, because we tend to fire this kiln for longer
(four to five days), the accumulation of ash and the volume of flame borne
alkalis in contact with clay surfaces are increased, drawing dramatic
colouration from the clay bodies used. The increased duration is needed
in part to achieve an even temperature throughout the kiln. The early
part of the firings predominantly dry the kiln, which gets damp from being
quite exposed. One of the most valuable assets of this kiln is that the
wood is stoked onto a flat floor which also becomes the front packing
space, this allows work to be stacked where it can be engulfed by the
coals, producing wonderful charred and fire marked surfaces.
In February of 2006, Steve, Matthew Blakely and myself fired the kiln for
the last time in this incarnation. For years we had often discussed the possibility
of extending the front of the kiln to allow both for a grate to be fitted
and also to create more packing space. The grate issue was a big drive for
us. The air that could be let into the firebox was so limited and made it
very hard to achieve the sorts of temperatures that we wanted. Air could only
enter the firebox through the lower stoke hole, which meant that the coals
burnt down either very quickly in the middle or, if the stoke hole was closed,
the coals would stay too high to stoke enough fuel to gain temperature. After
the February firing we decided that we would take the plunge and finally rebuild
the kiln.
We began work on dismantling the front of the kiln in
July 2006. As stated earlier the major asset that we wanted to build upon
was the flat stacking space/firebox floor, increasing the space available
for this zone. Also creating space for a large grate that would allow
us to control the air being drawn into the kiln beneath the coals and
being drawn up and pre-heated by them. The first job however was to knock
down the existing front of the kiln. As the original front curved in from
the sides towards the front we had to take the kiln back to just before
this curvature started. This done, we marked out where we wanted the new
firebox to be, working on the dimensions relative to what would finally
be the overall packing space, the exit flue space and the chimney dimensions.
(When the chimney was rebuilt the dimensions were kept generous to allow
for alterations). The foundations were placed and a brick floor for the
bottom of the grate was laid. Once this was done, a dry run was laid out
to visualise where the sidewalls, and the door would sit. Our plan was
to have the height of the grate the same as the old kiln floor. Once the
outline had been agreed the bricks were motored in place using a fireclay/sand
mortar. Also the front hot wall of the under grate area was built, in
the process cleaning up the front of the old firebox area.
One of the problems which we anticipated was our ability
to tie in the new structure to the old, due to the old kiln front being
constructed using many small cut bricks (Please
click here to view images from the original kiln building). The line
to which we took the front back to, did not provide us with clear regular
keying in points. We had to create some of these by knocking out half
bricks in several places up the vertical wall and remaining arch, creating
points which could be built out from.
When the vertical walls were nearing completion, we
began work on the former for the arch. We wanted to stay as true as possible
to the original sweep of this arch from front to back. Two cross section
formers were built initially, the first to support the existing arch and
the second to indicate the door height. (The height of the door had to
allow for the grate and provide us with enough drop to allow us to stoke
plenty of fuel into the firebox). Using flexible lathes we constructed
the front to back curve of the arch and then cut two more cross section
formers to provide some added strength. More lathes were laid from the
back section of the kiln to the new front wall. Once the former was complete
we could continue with the brickwork, building in two side stoke holes
on either side. The first enabling us to side stoke into the firebox and
the second to allow us to side stoke into the new flat packing space.
At the point where the arch springs from the vertical wall a layer of
inwardly tapering bricks were laid to change the direction of the hot
face bricks, then subsequent layers of brick were laid along the line
of the former with the first few courses being corbelled in to cover the
left and right corners of the new firebox. The same method of tying in
was used as in the vertical walls trying our best to interlock as many
of the new courses with the old. Towards the top of the first brick arch,
a row of bricks was laid on end down either side to act as a lock for
the second layer of bricks. The key to this first arch was then formed
using brick and rammed high temperature castable. A small blowhole was
placed just above the new front packing space, a place to heat the kettle
as much as a future guide to back pressure within the kiln. Any gaps between
the back edges of the bricks were then rammed with dry fireclay creating
a very strong primary arch.
The second layer of arch bricks were then laid over the top of the first
ensuring that no brick meeting points duplicated the interior arch. These
were locked into the up ended bricks in the primary arch and again the
key brick was cast with high temperature castable and brick. Finally this
secondary arch was rammed with fireclay to create a solid arch. Any holes
that were unavoidably left where the new structure keyed into the old
were also rammed with castable on both the primary and secondary arches.
The internal kiln structure was complete.
The next job was to provide substantial buttressing
for the new kiln. Due to restricted space around the kiln we decided on
concrete to reinforce the structure. Roughly one ton of concrete was mixed
for each side of the kiln and shuttered up the front and sides to just
above where the arch sprang off the vertical walls The front corners of
the kiln were identified as key points which needed strong reinforcement
so plenty of concrete was cast at these points. It was also cast back
and bonded to the existing concrete on the back half of the structure.
New concrete was also added to the old, to raise the height, again to
above the arch springing point and capped with heavy stones. Separate
sections around the four side stoke holes were cast and bridged by stone.
Finally the flue which extends for about a metre from the back of the
chamber to the base of the chimney was re coated with a sand, fireclay,
pearlite and cement mix to fill any cracks which had appeared over the
years and once again make a good seal between the two structures.
With the eight hundred heavy bricks which we had to
re-build the kiln we also acquired over a thousand secondary insulation
bricks. It was decided that we would use these to provide the new kiln
with good insulation. The previous incarnation of the kiln did not have
any insulation to speak of, simply a skim of cement with a little straw
mixed in. The capping stones for the concrete buttressing were then used
as a bed to start laying these insulation bricks. Laid broad face on to
the heavy brick structure and bedded in place with a fireclay and sand
mortar. Being easy to cut with a saw made the job of keying this final
arch at the top easier and again any gaps between the outside edges of
these bricks were rammed with dry fireclay so that this final arch was
also tensioned. Finally two large concrete slabs were laid at the front
of the kiln, to provide a good stable working space when packing and stoking.
In mid November 2006 the new incarnation of the Wysing anagama was complete.
It had taken roughly six days work to get the kiln to this stage.
The kiln is now being left alone until January with the former still in place
to allow the concrete to cure slowly and the whole structure to settle down.
We aim to resume the work in the new year. This will consist of removing the
former and cleaning up the brickwork from the inside and ramming any gaps
which exist between the new and old structures internally. We are also going
to extend the kiln shed to accommodate the longer kiln. We are aiming to fire
the kiln for the first time in February 2007. This firing and the results
will be posted on the site. Please
click here to view packing, firing and unpacking images from this firing.
Ben Brierley 2007
top
Back |